Fast Track Permitting System

Here at the City, we understand that time is money. The timeline of the general development process is as follows.

Entitlement Process

  • 2-week pre-application review process (no fees required)
  • 3-2-1 Process: 3-week review of initial formal submittal, 2-week review of resubmittals, 1-week condition of approval preparation
  • Public Hearings are scheduled approximately 5 weeks from hearing date
Grading Plan Process
  • No appointment needed for plan submittal
  • 5-week total City review process (from complete submittal to mylar approval)
Construction Process
The construction process includes building and fire permits.
  • 10-12 business days for initial review period
  • 5-7 business days for resubmittal review period
  • Inspections within 24-48 hours of request
More Information
For additional information on our development process, please contact the City of Temecula Planning Department at 951-694-6400.